Soft ground under a new embankment, or the backfill around a culvert, can move if load arrives faster than the soil can carry it. Measured pressure during construction shows how the load is building.

Why monitor during construction

Placing fill raises the load on the ground below layer by layer. On soft or wet ground the soil needs time to carry the extra load. If fill goes up too fast, settlement or movement can start. Around culverts and buried structures, uneven backfill can load one side more than the other.

What to measure

How MT-16 is set up

Pressure cells are placed at the base before fill begins and connected to an MT-16 at the edge of the site. The logger records through the whole build and sends the numbers to the site engineer every day, even when nobody is on site.

What you get

Using vibrating-wire piezometers or pressure cells? They can be connected through an RS-485 interface module.